Project Description

Techny Road
The improvements to Techny Road include the installation of a 72-inch and 84-inch relief sewer from Pfingsten Road to Second Street, the installation of storm sewers to drain the roadway, the removal and reconstruction of the center 24 feet of pavement and milling and resurfacing the remainder of the pavement from west of Pfingsten Road to Birch Road, the reconstruction of the pavement from Birch Road to Second Street, the installation of new traffic signals at Pfingsten Road, the grading of ditches and the installation of topsoil and sod.

Pfingsten Road
The improvements to Pfingsten Road include the installation of a 48-inch relief storm sewer from Canterbury Drive to Techny Road, pavement patching as required for the storm sewer installation, and restoration of parkways with topsoil and sod as required for the storm sewer installation.

Anticipated Start Date: May 21, 2012; dependent on weather and utility relocation work currently being performed.

Wednesday, November 28, 2012

Is it already December 2013?

On November 15, 2012; Techny Road was reopened to both eastbound and westbound traffic, a full year ahead of schedule.  The only remaining major work that still needs to be completed for this project is the installation of the traffic signals at the intersection of Techny Road and Pfingsten Road.  It is currently anticipated that this work will begin around December 10, 2012.  The traffic signals will take approximately 3 to 4 weeks to install and should not affect traffic.


Techny Road, west of Western Avenue, looking east.


Techny Road, west of Greenview Road, looking west.


Techny Road, east of Mallard Drive, looking east.