Project Description
Techny Road
The improvements to Techny Road include the installation of a 72-inch and 84-inch relief sewer from Pfingsten Road to Second Street, the installation of storm sewers to drain the roadway, the removal and reconstruction of the center 24 feet of pavement and milling and resurfacing the remainder of the pavement from west of Pfingsten Road to Birch Road, the reconstruction of the pavement from Birch Road to Second Street, the installation of new traffic signals at Pfingsten Road, the grading of ditches and the installation of topsoil and sod.
Pfingsten Road
The improvements to Pfingsten Road include the installation of a 48-inch relief storm sewer from Canterbury Drive to Techny Road, pavement patching as required for the storm sewer installation, and restoration of parkways with topsoil and sod as required for the storm sewer installation.
Anticipated Start Date: May 21, 2012; dependent on weather and utility relocation work currently being performed.
The improvements to Techny Road include the installation of a 72-inch and 84-inch relief sewer from Pfingsten Road to Second Street, the installation of storm sewers to drain the roadway, the removal and reconstruction of the center 24 feet of pavement and milling and resurfacing the remainder of the pavement from west of Pfingsten Road to Birch Road, the reconstruction of the pavement from Birch Road to Second Street, the installation of new traffic signals at Pfingsten Road, the grading of ditches and the installation of topsoil and sod.
Pfingsten Road
The improvements to Pfingsten Road include the installation of a 48-inch relief storm sewer from Canterbury Drive to Techny Road, pavement patching as required for the storm sewer installation, and restoration of parkways with topsoil and sod as required for the storm sewer installation.
Anticipated Start Date: May 21, 2012; dependent on weather and utility relocation work currently being performed.
Monday, April 30, 2012
Monday, April 16, 2012
Who is NPL?
If you have seen NPL trucks and equipment along Techny Road near Western Avenue and have been wondering what they are up to, here is the answer. NPL (Northern Pipe Line) is an utility contractor hired by Nicor to install new gas main and gas services along Techny Road from Cypress Lane to Second St. This work is required since the existing gas main is located where the new storm sewer is to be installed.
Subscribe to:
Posts (Atom)